RAMS NL-2291: Reframe the camera in Heron 2.02
Demo template. A demo template, not professional safety advice. A competent person must check every RAMS against the site, the work and the law where it happens before anyone relies on it.
Generated from the record, reviewed by Sam Okafor
- Client
- Aigna
- Site
- Juneau office, 2.02 Heron
- When
- Mon 5 Oct
- Crew
- Sam Okafor, Leo Hart, Maya Brooks
- For
- SNAG-14-02 · visit at risk
- Generated
- 25 Sep 2026, 14:00
The work, and what the record says
- Configure and test · Listed on the job
- Aigna's floor record: ceiling 2.7 m (Juneau office, second floor), shared on this job
- Aigna's floor record: cable tray in the corridor ceiling at 3.1 m (Juneau office, second floor)
- Aigna's record: 2.08 Comms room (MDF). Comms room in the core, beside riser 1; the riser cupboard opens into it. The same place on every floor
- Aigna's floor record: Riser 1 (data), fire-stopped at each floor
- Aigna's project PRJ-14: a fit-out, not yet open (handover target 16 Oct 2026)
Risk after controls
Likelihood up, 1 rare to 5 almost certainSeverity across, 1 to 5
Low, 1 to 4Medium, 5 to 12High, 15 and above
Before controls: 0 high, 1 medium, 0 low.
Hazards and controls
H1Other trades on an active fit-out
The office is still a construction site: other trades, open floors and moving materials.
- Who might be harmed
- The crew; Other trades
- Controls
- Site induction before work; the site manager's rules and permits followed
- Hard hat, high-visibility vest and safety boots on the floor
- A site safety card for everyone on the crew
Source: Aigna's project PRJ-14: a fit-out, not yet open (handover target 16 Oct 2026)
Before Medium · 3 × 4After Medium · 2 × 3
Method statement
- Before the visit. This RAMS approved and briefed to the crew; badges, induction and access confirmed; kit reserved and loaded.
- Arrive and sign in. Sign in with Aigna's site contact and the site manager; agree the work area and any times to avoid. (H1)
- Set up the work area. Mark the work area; check the route in for other trades' materials. (H1)
- Configure and test. Each unit set up from its setup guide; the room test run and recorded on the job.
- Clear up and hand back. Waste and packaging removed; the area handed back to the site contact; the as-built recorded on the job.
Personal protective equipment
- Safety boots
- Hard hat
- High-visibility vest
Emergency arrangements
- First aider on the crew: Sam Okafor
- The site's fire alarm, assembly point and first aiders: confirmed at induction (not in the record)
- Emergency services: 911
- Report any incident to Aigna's site contact and to Northlight's safety lead the same day
Competence: the crew's certifications
- Site safety card, everyone on the visitAn active fit-out site. In date on Mon 5 Oct.
- CTS, at least one personConfigure and test to the setup guides. In date on Mon 5 Oct.
Certifications from Northlight's crew record (Sam Okafor, Leo Hart, Maya Brooks), checked on the last day of the work. 9 kinds are tracked, from CTS to site safety cards.
Review and sign-off
| Briefed to | Role | Signature | Date |
|---|---|---|---|
| Sam Okafor | Project engineer | ||
| Leo Hart | Installer | ||
| Maya Brooks | AV engineer |