RAMS · NL-2318Simulated

Juneau fit-out: Wren 2.03 and the flex desks 2.07

8 hazards · highest after controls: Medium · waiting for review

RAMS NL-2318: Juneau fit-out: Wren 2.03 and the flex desks 2.07

Demo template. A demo template, not professional safety advice. A competent person must check every RAMS against the site, the work and the law where it happens before anyone relies on it.

Generated from the record, waiting for review

Client
Aigna
Site
Juneau office, 2.03 Wren, 2.07 Flex desks A
When
Mon 5 Oct to Wed 7 Oct
Crew
Sam Okafor, Leo Hart, Maya Brooks
For
PRJ-14 · visit at risk
Generated
28 Sep 2026, 09:00

The work, and what the record says

  • Configure and test · Listed on the job
  • Mount displays on the wall · 1 × Display, 43 in, for huddle rooms
  • Run and terminate cable · 1 × Display, 43 in, for huddle rooms, 1 × Logitech MeetUp 2, 1 × Cat 6A cable, 305 m box
  • Wall-mount a camera or video bar · 1 × Logitech MeetUp 2
  • Set up desk monitors · 8 × Dell UltraSharp 27 Thunderbolt Hub Monitor (U2724DE)
  • Work in the comms room · Cables end in 2.08 Comms room (MDF)
  • Electrical work by others · Power and data at the display walls by Aigna's facilities team (T-1403, done by 31 Jul 2026)
  • Aigna's floor record: ceiling 2.7 m (Juneau office, second floor), shared on this job
  • Aigna's floor record: cable tray in the corridor ceiling at 3.1 m (Juneau office, second floor)
  • Aigna's record: 2.08 Comms room (MDF). Comms room in the core, beside riser 1; the riser cupboard opens into it. The same place on every floor
  • Aigna's floor record: Riser 1 (data), fire-stopped at each floor
  • Aigna's project PRJ-14: a fit-out, not yet open (handover target 16 Oct 2026)
  • Aigna's project PRJ-14, task T-1403

Risk after controls

Likelihood up, 1 rare to 5 almost certainSeverity across, 1 to 5

Low, 1 to 4Medium, 5 to 12High, 15 and above

Before controls: 1 high, 7 medium, 0 low.

Hazards and controls

  1. H1Working at height

    Work above 2 m: cable tray at 3.1 m.

    Who might be harmed
    The crew; Other trades on site below (dropped tools)
    Controls
    • Podium steps with guard rails; a leaning ladder only for short access
    • Only people with in-date working at height training work above 2 m
    • The area below kept clear with barriers and a sign
    • Tools on lanyards; nothing loose on the platform

    Source: Aigna's floor record: cable tray in the corridor ceiling at 3.1 m (Juneau office, second floor)

    Before High · 3 × 5After Medium · 1 × 5
  2. H2Lifting and carrying

    Displays lifted onto wall mounts; 8 monitors carried in their boxes.

    Who might be harmed
    The crew
    Controls
    • Two people for every display lift
    • A trolley from the lift to the space; boxes opened where the kit is fitted
    • Clear route agreed before moving kit

    Source: Display, 43 in, for huddle rooms: no weight in the device library, so treated as a two-person lift. Dell UltraSharp 27 Thunderbolt Hub Monitor (U2724DE): 5.23 kg each, 8 of them (device library)

    Before Medium · 3 × 3After Low · 2 × 2
  3. H3Hidden cables and pipes when drilling

    Fixings for mounts and brackets go into walls or ceilings that may hide power cables or pipes.

    Who might be harmed
    The crew; Other trades on site
    Controls
    • A cable and pipe detector over every fixing point before drilling
    • Fixings only where the client's drawings or the site contact confirm it is clear
    • Stop and report anything unexpected

    Source: Tasks: mount displays on the wall (1 × Display, 43 in, for huddle rooms); Tasks: wall-mount a camera or video bar (1 × Logitech MeetUp 2)

    Before Medium · 2 × 4After Low · 1 × 4
  4. H4Electrical work by others

    Power and data at the display walls by Aigna's facilities team (T-1403, done by 31 Jul 2026). Northlight fits plug-in and low-voltage kit only.

    Who might be harmed
    The crew
    Controls
    • No work on fixed wiring: only the client's electrician opens a socket or a board
    • Every outlet checked with a socket tester before kit is plugged in
    • Faults reported to the site contact, never fixed by the crew

    Source: Aigna's project PRJ-14, task T-1403

    Before Medium · 2 × 5After Medium · 1 × 5
  5. H5Work beside live equipment in the comms room

    2.08 Comms room (MDF): patching beside switches that carry the building's network.

    Who might be harmed
    The crew; Everyone on the client's network (an outage)
    Controls
    • Access approved by the client; the rack left as found
    • Only the ports on the job touched; live patching never moved
    • No food or drink in the room

    Source: Aigna's record: 2.08 Comms room (MDF). Comms room in the core, beside riser 1; the riser cupboard opens into it. The same place on every floor

    Before Medium · 2 × 3After Low · 1 × 3
  6. H6Fire stopping in the riser

    Riser 1 (data) opens into the comms room; fire-stopped at each floor. A cable through it could break the fire stopping.

    Who might be harmed
    Everyone on site
    Controls
    • No new cable through the riser without the client's permit
    • Any fire stopping disturbed is made good the same day and photographed
    • The photo goes on the as-built

    Source: Aigna's floor record: Riser 1 (data), fire-stopped at each floor

    Before Medium · 2 × 5After Medium · 1 × 5
  7. H7Other trades on an active fit-out

    The office is still a construction site: other trades, open floors and moving materials.

    Who might be harmed
    The crew; Other trades
    Controls
    • Site induction before work; the site manager's rules and permits followed
    • Hard hat, high-visibility vest and safety boots on the floor
    • A site safety card for everyone on the crew

    Source: Aigna's project PRJ-14: a fit-out, not yet open (handover target 16 Oct 2026)

    Before Medium · 3 × 4After Medium · 2 × 3
  8. H8Trips over cable, cuts from tray edges

    Cable pulled across floors and through tray and ceiling grid with sharp edges.

    Who might be harmed
    The crew; Other trades on site
    Controls
    • Cable pulled in one run and dressed away at once
    • Gloves when handling tray and ceiling grid
    • Offcuts and packaging cleared as the work goes

    Source: Task: run and terminate cable (1 × Display, 43 in, for huddle rooms, 1 × Logitech MeetUp 2, 1 × Cat 6A cable, 305 m box)

    Before Medium · 3 × 2After Low · 1 × 2

Method statement

  1. Before the visit. This RAMS approved and briefed to the crew; badges, induction and access confirmed; kit reserved and loaded.
  2. Arrive and sign in. Sign in with Aigna's site contact and the site manager; agree the work area and any times to avoid. (H7)
  3. Set up the work area. Mark the work area; check the route in for other trades' materials. (H7)
  4. Bring the kit in. Trolley from the lift; two people for every display; boxes opened where the kit is fitted. (H2)
  5. Run the cable. From podium steps at 3.1 m; dressed away as it goes. (H1, H8)
  6. Mount the kit. Detector over each fixing point, then the mount; the display lifted on by two people and locked. (H2, H3)
  7. Set up the desk monitors. Each monitor on its arm or stand, cabled to the dock, tested at the desk. (H2)
  8. Patch in the comms room. Only the job's ports; fire stopping checked and photographed before leaving. (H5, H6)
  9. Configure and test. Each unit set up from its setup guide; the room test run and recorded on the job.
  10. Clear up and hand back. Waste and packaging removed; the area handed back to the site contact; the as-built recorded on the job.

Personal protective equipment

  • Safety boots
  • Hard hat
  • High-visibility vest
  • Gloves
  • Eye protection when drilling
  • Dust mask when drilling or in the ceiling void

Emergency arrangements

  • First aider on the crew: Sam Okafor
  • The site's fire alarm, assembly point and first aiders: confirmed at induction (not in the record)
  • Emergency services: 911
  • Report any incident to Aigna's site contact and to Northlight's safety lead the same day

Competence: the crew's certifications

  • Working at height, everyone on the visitWork above 2 m. Working at height for Maya expired 15 Sep.
  • Site safety card, everyone on the visitAn active fit-out site. In date on Wed 7 Oct.
  • CTS, at least one personConfigure and test to the setup guides. In date on Wed 7 Oct.

Certifications from Northlight's crew record (Sam Okafor, Leo Hart, Maya Brooks), checked on the last day of the work. 9 kinds are tracked, from CTS to site safety cards.

Review and sign-off

PreparedGenerated from the record28 Sep 2026, 09:00 · from the space, the job's tasks and the crew's certifications
ReviewWaiting for reviewA competent person reads every hazard and its controls, then approves. The visit waits until then.
Briefed toRoleSignatureDate
Sam OkaforProject engineer
Leo HartInstaller
Maya BrooksAV engineer

A provider's own Keia

This is Northlight AV's own operations

Stock, orders, crews and safety paperwork are Northlight AV's own records. They never flow to a client: a client sees only the visit readiness and the handover packs its engagement shares. To see them, pick Sam Okafor (Northlight AV) in View as.

See Aigna's engagement with Northlight AV

View as

See Keia Atlas the way someone else does. A demo: nobody signs in.

Viewing asAnna ByrneAV and IT delivery engineer · EMEA

Suggested

Delivery

  • Delivery engineerDesigns and commissions spaces, from survey to handover
  • Project managerRuns projects day to day: dates, suppliers and who does what
  • On-site technicianInstalls and fixes kit in the offices
  • Programme managerPlans the year of projects across every region
  • Engineering managerLeads the delivery engineers
  • Project management leadLeads the project managers
  • On-site services managerLeads the on-site technicians
  • Delivery managerThe whole delivery team, every region

Support and service

  • Service desk analystTakes incidents as they arrive and routes them
  • Network engineerPorts, VLANs and patching
  • Service manager, AVOwns the AV standard and its service
  • Service manager, networkOwns the network standard and its service

The Lab

  • Innovation engineerTests new kit before it ships

Leadership

  • Head of AV and ITThe whole service, every region

Partners

  • Integration vendorSees their own installations only
  • Service vendorRepairs under the service contract

Overview

  • EveryoneEvery role's first screen at once, to see the whole picture

Settings

Appearance
LookStudio
Text size
Default

Report

Tell the team

About RAMS: Juneau fit-out: Wren 2.03 and the flex desks 2.07

Goes to Sofia Reyes, Service manager, AV. Reviewed within five working days.