Workplace IT refresh

Version 1.0 · no live project follows itchecked just now

Phases

6 phases, 23 steps. Pick one to see its steps.
  1. 01Plan1 to 2 weeks4
  2. 02Design1 to 2 weeks4
  3. 03Procure3 to 6 weeks3
  4. 04DeployOne day per floor, then 19
    Provision2Install2Configure2Commission3
  5. 05Hand over1 week2
  6. 06ClosedWrap-up1

Long lead: needs starting early

Projects using it

No project uses this playbook yet.

New project

Steps and gates

Each phase ends at a gate a named role signs off before the next starts.
  1. 01

    Plan

    1 to 2 weeks
    AB +3AV and IT delivery engineerPull the printers, signage players and booking panels past their years in service from the refresh planProduces: List of units due
    SRService manager, AVConfirm the current standard model for each kind of device
    RK +3Project managerAgree a floor order and quiet weeks with facilitiesProduces: Floor order
    TVProgramme managerBudget line and purchase request
    Gate: signed off by Programme manager
    • Scope and budget agreed
    • Floors fit the year plan
  2. 02

    Design

    1 to 2 weeks
    AB +3AV and IT delivery engineerSwap sheet per floor: position, old model, new model, hostname and address keptProduces: Swap sheet
    AB +3AV and IT delivery engineerCheck mounts, supplies, cables and power suit the new model
    AB +3AV and IT delivery engineerTake the configuration from each new model's configuration page
    MB FINetwork engineerCheck each print queue, signage playlist and booking panel link that has to carry overProduces: Links to carry over
    Gate: signed off by Service manager, AV
    • Every swap is to the current standard
    • Nothing that depends on the old device is missed
  3. 03

    Procure

    3 to 6 weeks
    RK +3Project managerOrder units, mounts and one spare per tenLong lead: start early
    MB FINetwork engineerSend MACs to the network team for address reservations before delivery
    LD +8On-site technicianRecord serials on arrival against the swap sheet
    Gate: signed off by Project manager
    • Everything received
    • Addresses reserved
  4. 04

    Deploy

    One day per floor, then 1

    Provision

    LD +8On-site technicianRetire the old unit in the asset register the same day
    AB +3AV and IT delivery engineerAdd the new unit to device management and monitoring

    Install

    RK +3Project managerTell the floor which day the printers and panels will be off
    LD +8On-site technicianSwap the unit, keeping position and hostname

    Configure

    AB +3AV and IT delivery engineerConfigure each device in its setup order, then set and verify its settings
    MB FINetwork engineerPoint print queues, signage playlists and booking links at the new device

    Commission

    AB +3AV and IT delivery engineerRun the verification for each device
    LD +8On-site technicianPrint, display and book a test from the floor
    AB +3AV and IT delivery engineerSnag listProduces: Snag list
    Gate: signed off by AV and IT delivery engineer
    • Every floor in the batch installed
    • Every device passes, or its snags are accepted
  5. 05

    Hand over

    1 week
    RK +3Project managerHandover note to the service desk: what changed on each floorProduces: Handover note
    RK +3Project managerRedeploy or dispose of the old units
    Gate: signed off by Service manager, AV
    • Records match what is on the floors
  6. 06

    Closed

    RK +3Project managerFeed what was learned back into this playbook
    Gate: signed off by Programme manager
    • Lessons captured

Who does what

Built from the steps and gates above. Hover a letter for the steps.
  • ResponsibleDoes the work.
  • AccountableSigns it off and answers for it. One per row.
  • ConsultedIs asked before it is done.
  • InformedIs told once it is done.
RACI for the Workplace IT refresh playbook
WorkService manager, AVProgramme managerProject managerAV and IT delivery engineerNetwork engineerOn-site technician
Plan1 to 2 weeksRService manager, AV · ResponsibleFor “Plan”, the service manager, av does the work.Confirm the current standard model for each kind of device.Today: Sofia ReyesAProgramme manager · AccountableFor “Plan”, the programme manager signs it off and answers for it.Signs the gate: Scope and budget agreed; Floors fit the year plan. Also does: Budget line and purchase request.Today: Tomás VargaRProject manager · ResponsibleFor “Plan”, the project manager does the work.Agree a floor order and quiet weeks with facilities.Today: Ruth Kelly, Katya Novak, David Okoro and 1 moreRAV and IT delivery engineer · ResponsibleFor “Plan”, the av and it delivery engineer does the work.Pull the printers, signage players and booking panels past their years in service from the refresh plan.Today: Anna Byrne, Marcus Lee, Mei Tan and 1 more
Design1 to 2 weeksAService manager, AV · AccountableFor “Design”, the service manager, av signs it off and answers for it.Signs the gate: Every swap is to the current standard; Nothing that depends on the old device is missed.Today: Sofia ReyesIProject manager · InformedFor “Design”, the project manager is told once it is done.Kept up to date to run the dates.Today: Ruth Kelly, Katya Novak, David Okoro and 1 moreRAV and IT delivery engineer · ResponsibleFor “Design”, the av and it delivery engineer does the work.Swap sheet per floor: position, old model, new model, hostname and address kept; Check mounts, supplies, cables and power suit the new model; Take the configuration from each new model's configuration page.Today: Anna Byrne, Marcus Lee, Mei Tan and 1 moreRNetwork engineer · ResponsibleFor “Design”, the network engineer does the work.Check each print queue, signage playlist and booking panel link that has to carry over.Today: Marco Bianchi, Farah Idris
Procure3 to 6 weeksAProject manager · AccountableFor “Procure”, the project manager signs it off and answers for it.Signs the gate: Everything received; Addresses reserved. Also does: Order units, mounts and one spare per ten.Today: Ruth Kelly, Katya Novak, David Okoro and 1 moreRNetwork engineer · ResponsibleFor “Procure”, the network engineer does the work.Send MACs to the network team for address reservations before delivery.Today: Marco Bianchi, Farah IdrisROn-site technician · ResponsibleFor “Procure”, the on-site technician does the work.Record serials on arrival against the swap sheet.Today: Liam Doyle, Tom Ashby, Carlos Mendes and 6 more
DeployOne day per floor, then 1RProject manager · ResponsibleFor “Deploy”, the project manager does the work.Tell the floor which day the printers and panels will be off.Today: Ruth Kelly, Katya Novak, David Okoro and 1 moreAAV and IT delivery engineer · AccountableFor “Deploy”, the av and it delivery engineer signs it off and answers for it.Signs the gate: Every floor in the batch installed; Every device passes, or its snags are accepted. Also does: Add the new unit to device management and monitoring; Configure each device in its setup order, then set and verify its settings; Run the verification for each device; Snag list.Today: Anna Byrne, Marcus Lee, Mei Tan and 1 moreRNetwork engineer · ResponsibleFor “Deploy”, the network engineer does the work.Point print queues, signage playlists and booking links at the new device.Today: Marco Bianchi, Farah IdrisROn-site technician · ResponsibleFor “Deploy”, the on-site technician does the work.Retire the old unit in the asset register the same day; Swap the unit, keeping position and hostname; Print, display and book a test from the floor.Today: Liam Doyle, Tom Ashby, Carlos Mendes and 6 more
Hand over1 weekAService manager, AV · AccountableFor “Hand over”, the service manager, av signs it off and answers for it.Signs the gate: Records match what is on the floors.Today: Sofia ReyesRProject manager · ResponsibleFor “Hand over”, the project manager does the work.Handover note to the service desk: what changed on each floor; Redeploy or dispose of the old units.Today: Ruth Kelly, Katya Novak, David Okoro and 1 more
ClosedAProgramme manager · AccountableFor “Closed”, the programme manager signs it off and answers for it.Signs the gate: Lessons captured.Today: Tomás VargaRProject manager · ResponsibleFor “Closed”, the project manager does the work.Feed what was learned back into this playbook.Today: Ruth Kelly, Katya Novak, David Okoro and 1 more

What projects have taught it

1 change
  • 20 Oct 2026First version.

View as

See Keia Atlas the way someone else does. A demo: nobody signs in.

Viewing asAnna ByrneAV and IT delivery engineer · EMEA

Suggested

Delivery

  • Delivery engineerDesigns and commissions spaces, from survey to handover
  • Project managerRuns projects day to day: dates, suppliers and who does what
  • On-site technicianInstalls and fixes kit in the offices
  • Programme managerPlans the year of projects across every region
  • Engineering managerLeads the delivery engineers
  • Project management leadLeads the project managers
  • On-site services managerLeads the on-site technicians
  • Delivery managerThe whole delivery team, every region

Support and service

  • Service desk analystTakes incidents as they arrive and routes them
  • Network engineerPorts, VLANs and patching
  • Service manager, AVOwns the AV standard and its service
  • Service manager, networkOwns the network standard and its service

The Lab

  • Innovation engineerTests new kit before it ships

Leadership

  • Head of AV and ITThe whole service, every region

Partners

  • Integration vendorSees their own installations only
  • Service vendorRepairs under the service contract

Overview

  • EveryoneEvery role's first screen at once, to see the whole picture