Keia Atlas · Work report
London office meeting room refresh
CompletedGenerated 19 Oct 2026
- Project
- PRJ-09 London office meeting room refresh
- Office
- London office
- Kind of work
- AV refresh, following the AV refresh playbook version 1.4
- Started
- 23 Feb 2026
- Target
- 10 Jul 2026
- Finished
- 10 Jul 2026
- Project manager
- Ruth Kelly
- Spaces
- 2.01 Kestrel, 2.02 Heron, 2.03 Curlew
- Cost
- £47,100 spent of £52,000 approved
What was done
Replaced the first-generation video bars in Kestrel, Heron and Curlew with the current standard, keeping positions and hostnames.
- PlanEnded 5 Mar 2026, signed off by Tomás VargaThree rooms in one batch; budget agreed.
- DesignEnded 19 Mar 2026, signed off by Sofia ReyesLike-for-like swap; Curlew needed a longer HDMI run for the new bar.
- ProcureEnded 29 Apr 2026, signed off by Ruth KellyUnits five days late; MAC reservations were requested only after delivery, which cost two days.
- DeployEnded 11 Jun 2026, signed off by Anna ByrneAll three rooms swapped over two evenings. All rooms pass; one snag on Curlew camera framing, fixed on the day.
- Hand overEnded 3 Jul 2026, signed off by Sofia ReyesOld units redeployed to training rooms.
- ClosedEnded 10 Jul 2026, signed off by Tomás VargaTwo lessons fed back into the AV refresh playbook.
Charter
The first-generation video bars in Kestrel, Heron and Curlew are past their years in service and out of support. Swap them for the current standard without changing what the rooms do.
Success looks like
- Three rooms on the current standard video bar, each passing verification
- Every position and hostname kept, so booking and monitoring never notice
- Old units redeployed or retired in the asset register the same day
Status at close
- Schedule: Closed on timeFine. Every gate signed off by 10 Jul.
- Cost: £4,900 in handFine. £47,100 spent or ordered of £52,000 approved.
- Scope: Changed once, approvedFine. 3 spaces; add one spare unit to the order was approved by Tomás Varga.
Who
- Tomás VargaProgramme manager8 of 8 hKept it in the year plan and held the budget
- Ruth KellyProject manager46 of 44 hRan dates, room bookings and the handover
- Anna ByrneLead engineer34 of 36 hSwap sheets, commissioning sign-off
- Tom AshbyTechnician42 of 40 hSwapped the units and ran the verification
- Marco BianchiNetwork engineer4 of 4 hAddress reservations
- Sofia ReyesService owner (sign-off)4 of 4 hConfirmed the standard model
Tasks 11 of 11 done
| Task | Owner | Due | How it closed |
|---|---|---|---|
| T-0901 Pull the units past their years in service | Anna Byrne | 3 Mar 2026 | Nothing new: the guide was right |
| T-0902 Budget line and purchase request | Tomás Varga | 5 Mar 2026 | Nothing new: not device related |
| T-0903 Swap sheet for Kestrel, Heron and Curlew | Anna Byrne | 19 Mar 2026 | Fix captured: Measure the HDMI run before ordering: the new bar sits 40 cm lower in Curlew. |
| T-0904 Order units, mounts and a spare | Ruth Kelly | 27 Mar 2026 | Nothing new: not device related |
| T-0905 Reserve addresses for the new units | Marco Bianchi | 29 Apr 2026 | Fix captured: Ask for reservations by MAC before the units ship, not after delivery. |
| T-0906 Swap the video bar in Kestrel | Tom Ashby | 27 May 2026 | Nothing new: the guide was right |
| T-0907 Swap the video bar in Heron | Tom Ashby | 27 May 2026 | Nothing new: the guide was right |
| T-0908 Swap the video bar in Curlew | Tom Ashby | 28 May 2026 | Fix captured: Retire the old unit in the asset register on the day of the swap, not at handover. |
| T-0909 Commission all three rooms | Anna Byrne | 11 Jun 2026 | Nothing new: the guide was right |
| T-0910 Hand over to the service desk | Ruth Kelly | 3 Jul 2026 | Nothing new: not device related |
| T-0911 Feed what was learned back into the playbook | Ruth Kelly | 10 Jul 2026 | Nothing new: a one-off |
Risks, issues, decisions and dependencies
| Id | Kind | What | Owner | Status |
|---|---|---|---|---|
| R-1 | Risk | Units arrive after the batch windowHappened, five days late; the batch moved by a week and still closed on time. | Ruth Kelly | Closed29 Apr |
| I-1 | Issue | Address reservations asked for after deliveryTwo days lost waiting on the network queue. Now a playbook step, and a lesson below. | Marco Bianchi | Resolved29 Apr |
| D-1 | Decision | Like-for-like swap, no change to wiring or space typesKeeps the rooms on the standard space type and the swap inside the AV refresh playbook. | Sofia Reyes | Decided19 Mar |
| X-1 | Dependency | Longer HDMI run for Curlew from facilitiesMeasured before the order, so it was on site before install. | Anna Byrne | Met10 Apr |
Changes to scope
- CR-1 Add one spare unit to the order: approved 25 Mar by Tomás Varga, +£8,400. One spare per ten is the playbook rule; three rooms rounds to one spare so a failed unit is swapped the same day.
Lessons learned
- "Measure the HDMI run before ordering: the new bar sits 40 cm lower in Curlew." (T-0903, Anna Byrne; in the playbook since 23 May)
- "Ask for reservations by MAC before the units ship, not after delivery." (T-0905, Marco Bianchi; in the playbook since 23 May)
- "Retire the old unit in the asset register on the day of the swap, not at handover." (T-0908, Tom Ashby; in the playbook since 23 May)
Devices installed or changed
| Space | Position | Model | Serial | Asset tag | Note |
|---|---|---|---|---|---|
| 2.01 Kestrel | Video barlon-201-vc01 | Poly Studio X52Standard firmware 4.6.2.460046 | DEMO-LON-001303 | AG-001303 | |
| 2.02 Heron | Video barlon-202-vc01 | Poly Studio X52Standard firmware 4.6.2.460046 | DEMO-LON-001308 | AG-001308 | |
| 2.03 Curlew | Video barlon-203-vc01 | Poly Studio X72Standard firmware 4.6.2.460046 | DEMO-LON-001314 | AG-001314 |
Evidence
- Plan: Scope and budget line
- Design: Swap sheet for three rooms
- Procure: Purchase order
- Procure: Serials on arrival
- Deploy: Install record per room
- Deploy: Verification results
- Deploy: Snag list (closed)
- Hand over: Handover note to the service desk
- Closed: Playbook change 1.2
Deviations and added tasks
- Procure ended 5 days after plan. Units five days late; MAC reservations were requested only after delivery, which cost two days.
- Hand over ended 7 days after plan. Old units redeployed to training rooms.
- T-0903 Swap sheet for Kestrel, Heron and Curlew: the guide did not cover it. Fix captured: Measure the HDMI run before ordering: the new bar sits 40 cm lower in Curlew.
- T-0905 Reserve addresses for the new units: the guide did not cover it. Fix captured: Ask for reservations by MAC before the units ship, not after delivery.
- T-0908 Swap the video bar in Curlew: the guide did not cover it. Fix captured: Retire the old unit in the asset register on the day of the swap, not at handover.
- Ruth Kelly logged 46 h against 44 h planned.
- Tom Ashby logged 42 h against 40 h planned.
Sign-off
- Plan: signed off by Tomás Varga, 5 Mar 2026
- Design: signed off by Sofia Reyes, 19 Mar 2026
- Procure: signed off by Ruth Kelly, 29 Apr 2026
- Deploy: signed off by Anna Byrne, 11 Jun 2026
- Hand over: signed off by Sofia Reyes, 3 Jul 2026
- Closed: signed off by Tomás Varga, 10 Jul 2026
- Closed 10 Jul 2026, signed off by Tomás Varga