Keia Atlas · Work report
Swap sheet for Kestrel, Heron and Curlew
DoneGenerated 19 Oct 2026
- Task
- T-0903 Swap sheet for Kestrel, Heron and Curlew
- Project
- PRJ-09 London office meeting room refresh
- Office
- London office
- Kind of work
- Design phase, design work
- Space
- Whole project
- Done by
- Anna Byrne, Lead engineer
- Due
- 19 Mar 2026
- Estimate
- 6 h
- Closed with the phase
- Design phase ended 19 Mar 2026
What was done
Swap sheet for Kestrel, Heron and Curlew. Fix captured: Measure the HDMI run before ordering: the new bar sits 40 cm lower in Curlew.
Steps followed
- Choose the build option for each space from its space type.
- Write the swap sheet: position, old model, new model, hostname kept.
- Check mounts, cable lengths and power suit the new model (its ports are on the model page).
- List each networked device with its port and VLAN for the network team.
- Ask the service manager for design sign-off.
Who
- Anna ByrneLead engineer6 h estimatedSwap sheets, commissioning sign-off
Devices installed or changed
No devices were installed or changed by this work.
Evidence
- Closing note: Measure the HDMI run before ordering: the new bar sits 40 cm lower in Curlew.
- Recorded for the Design phase: Swap sheet for three rooms
Deviations and added tasks
- The guide did not cover this. Fix captured: Measure the HDMI run before ordering: the new bar sits 40 cm lower in Curlew.
Sign-off
- Design gate: signed off by Sofia Reyes, 19 Mar 2026
- Task closed