Work reportDoneSimulated

Work report: Commission all three rooms

Complete · no differences from the planchecked just now

Back to the task

Keia Atlas · Work report

Commission all three rooms

DoneGenerated 19 Oct 2026

Task
T-0909 Commission all three rooms
Project
PRJ-09 London office meeting room refresh
Office
London office
Kind of work
Deploy phase, commission work
Space
Whole project
Done by
Anna Byrne, Lead engineer
Due
11 Jun 2026
Estimate
6 h
Closed with the phase
Deploy phase ended 11 Jun 2026

What was done

Commission all three rooms. Nothing new: the guide was right.

Steps followed

  1. Run the space's verification: every device recorded, on its address, in device management and on standard firmware.
  2. Make a test call from another site, not the space next door.
  3. Check camera framing and microphone levels from the far end.
  4. List any snags; each gets an owner and a date.
  5. Close with what fixed anything unexpected, or "Nothing new" and why.

Who

  • Anna ByrneLead engineer6 h estimatedSwap sheets, commissioning sign-off

Devices installed or changed

SpacePositionModelSerialAsset tagNote
2.01 KestrelDisplaylon-201-dsp01DEMO-LON-001301AG-001301
2.01 KestrelDisplaylon-201-dsp02DEMO-LON-001302AG-001302
2.01 KestrelVideo barlon-201-vc01Poly Studio X52Standard firmware 4.6.2.460046DEMO-LON-001303AG-001303
2.01 KestrelTouch controllerlon-201-tc01Poly TC10DEMO-LON-001304AG-001304
2.01 KestrelHDBaseT transmitterKramer EXT3-C-XR-TDEMO-LON-001305AG-001305
2.01 KestrelHDBaseT receiver at the displayKramer EXT3-POE-XR-RDEMO-LON-001306AG-001306
2.02 HeronDisplaylon-202-dsp01DEMO-LON-001307AG-001307
2.02 HeronVideo barlon-202-vc01Poly Studio X52Standard firmware 4.6.2.460046DEMO-LON-001308AG-001308
2.02 HeronTouch controllerlon-202-tc01Poly TC10DEMO-LON-001309AG-001309
2.02 HeronHDBaseT transmitterKramer EXT3-C-XR-TDEMO-LON-001310AG-001310
2.02 HeronHDBaseT receiver at the displayKramer EXT3-POE-XR-RDEMO-LON-001311AG-001311
2.03 CurlewDisplaylon-203-dsp01DEMO-LON-001312AG-001312
2.03 CurlewDisplaylon-203-dsp02DEMO-LON-001313AG-001313
2.03 CurlewVideo barlon-203-vc01Poly Studio X72Standard firmware 4.6.2.460046DEMO-LON-001314AG-001314
2.03 CurlewTouch controllerlon-203-tc01Poly TC10DEMO-LON-001315AG-001315
2.03 CurlewMicrophonePoly Studio Expansion MicrophoneDEMO-LON-001316AG-001316
2.03 CurlewMicrophonePoly Studio Expansion MicrophoneDEMO-LON-001317AG-001317
2.03 CurlewIn-room network switchlon-203-sw01Netgear AV Line M4250-9G1F-PoE+ (GSM4210PD)DEMO-LON-001318AG-001318
2.03 CurlewChooses between the laptop inputsKramer SWT3-31-HUDEMO-LON-001319AG-001319
2.03 CurlewHDBaseT transmitters, one per side tableKramer EXT3-C-XR-TDEMO-LON-001320AG-001320
2.03 CurlewHDBaseT transmitters, one per side tableKramer EXT3-C-XR-TDEMO-LON-001321AG-001321
2.03 CurlewHDBaseT receiversKramer EXT3-POE-XR-RDEMO-LON-001322AG-001322
2.03 CurlewHDBaseT receiversKramer EXT3-POE-XR-RDEMO-LON-001323AG-001323

Evidence

  • Closing note: Nothing new: the guide was right
  • Recorded for the Deploy phase: Install record per room
  • Recorded for the Deploy phase: Verification results
  • Recorded for the Deploy phase: Snag list (closed)

Deviations and added tasks

No deviations recorded.

Sign-off

  • Deploy gate: signed off by Anna Byrne, 11 Jun 2026
  • Task closed
Done byAnna ByrneSignatureDate
Project managerRuth KellySignatureDate

View as

See Keia Atlas the way someone else does. A demo: nobody signs in.

Viewing asAnna ByrneAV and IT delivery engineer · EMEA

Suggested

Delivery

  • Delivery engineerDesigns and commissions spaces, from survey to handover
  • Project managerRuns projects day to day: dates, suppliers and who does what
  • On-site technicianInstalls and fixes kit in the offices
  • Programme managerPlans the year of projects across every region
  • Engineering managerLeads the delivery engineers
  • Project management leadLeads the project managers
  • On-site services managerLeads the on-site technicians
  • Delivery managerThe whole delivery team, every region

Support and service

  • Service desk analystTakes incidents as they arrive and routes them
  • Network engineerPorts, VLANs and patching
  • Service manager, AVOwns the AV standard and its service
  • Service manager, networkOwns the network standard and its service

The Lab

  • Innovation engineerTests new kit before it ships

Leadership

  • Head of AV and ITThe whole service, every region

Partners

  • Integration vendorSees their own installations only
  • Service vendorRepairs under the service contract

Overview

  • EveryoneEvery role's first screen at once, to see the whole picture

Settings

Appearance
LookStudio
Text size
Default

Report

Tell the team

About T-0909 Commission all three rooms

Goes to Sofia Reyes, Service manager, AV. Reviewed within five working days.