Keia Atlas

Vendor access

This part is for Aigna staff

Vendors see their own installation and the device reference they need to build it: device types, setup guides and models. Everything else stays with Aigna.

Go to your installation

Module

Projects is switched off

Projects, the schedule, planning, the work plan and the Lab. This demo has the Projects module switched off in Organisation settings.

Organisation settings

Work reportDoneSimulated

Work report: Install cameras and ceiling microphones in Barn Owl

Complete · 1 difference from the planchecked just now

Back to the task

Keia Atlas · Work report

Install cameras and ceiling microphones in Barn Owl

DoneGenerated 19 Oct 2026

Task
T-1005 Install cameras and ceiling microphones in Barn Owl
Project
PRJ-10 Chicago office hybrid rooms
Office
Chicago office
Kind of work
Deploy phase, install work
Space
12.08 Barn Owl
Done by
Grace Kim, Technician
Due
10 Sept 2026
Estimate
10 h
Closed with the phase
Deploy phase ended 15 Oct 2026

What was done

Install cameras and ceiling microphones in Barn Owl. Nothing new: the guide was right.

Steps followed

  1. Book the space out for the time the install needs.
  2. Check the firmware on the unit against the standard. Newer than the standard? Don't update or roll back: use Report, New firmware found.
  3. Mount each device where the space type puts it, and connect it as the wiring shows.
  4. Power on and check each device takes its reserved address.
  5. Keep the position and hostname; retire any old unit in the asset register the same day.

Who

  • Grace KimTechnician10 h estimatedInstalls and verification

Devices installed or changed

SpacePositionModelSerialAsset tagNote
12.08 Barn OwlVideo barchi-1208-vc01Poly Studio X72Standard firmware 4.6.2.460046DEMO-CHI-000042AG-000042
12.08 Barn OwlMicrophonePoly Studio Expansion MicrophoneDEMO-CHI-000044AG-000044
12.08 Barn OwlMicrophonePoly Studio Expansion MicrophoneDEMO-CHI-000045AG-000045

Evidence

  • Closing note: Nothing new: the guide was right
  • Recorded for the Deploy phase: Install record per room
  • Recorded for the Deploy phase: Verification results
  • Recorded for the Deploy phase: Snag list

Deviations and added tasks

  • The Deploy phase ended 6 days after plan. Ceiling microphones needed a second visit for tile cut-outs. Both rooms pass. Microphone levels tuned after a test call from Dublin.

Sign-off

  • Deploy gate: signed off by Marcus Lee, 15 Oct 2026
  • Task closed
Done byGrace KimSignatureDate
Project managerDavid OkoroSignatureDate

View as

See Keia Atlas the way someone else does. A demo: nobody signs in.

Viewing asAnna ByrneAV and IT delivery engineer · EMEA

Suggested

Delivery

  • Delivery engineerDesigns and commissions spaces, from survey to handover
  • Project managerRuns projects day to day: dates, suppliers and who does what
  • On-site technicianInstalls and fixes kit in the offices
  • Programme managerPlans the year of projects across every region
  • Engineering managerLeads the delivery engineers
  • Project management leadLeads the project managers
  • On-site services managerLeads the on-site technicians
  • Delivery managerThe whole delivery team, every region

Support and service

  • Service desk analystTakes incidents as they arrive and routes them
  • Network engineerPorts, VLANs and patching
  • Service manager, AVOwns the AV standard and its service
  • Service manager, networkOwns the network standard and its service

The Lab

  • Innovation engineerTests new kit before it ships

Leadership

  • Head of AV and ITThe whole service, every region

Partners

  • Integration vendorSees their own installations only
  • Service vendorRepairs under the service contract

Overview

  • EveryoneEvery role's first screen at once, to see the whole picture

Settings

Appearance
LookStudio
Text size
Default

Report

Tell the team

About T-1005 Install cameras and ceiling microphones in Barn Owl

Goes to Sofia Reyes, Service manager, AV. Reviewed within five working days.