Draft the design and signal routes
DoneGenerated 19 Oct 2026
- Task
- T-1002 Draft the design and signal routes
- Project
- PRJ-10 Chicago office hybrid rooms
- Office
- Chicago office
- Kind of work
- Design phase, design work
- Space
- Whole project
- Done by
- Marcus Lee, Lead engineer
- Due
- 19 Jun 2026
- Estimate
- 16 h
- Closed with the phase
- Design phase ended 19 Jun 2026
What was done
Draft the design and signal routes. Nothing new: the guide was right.
Steps followed
- Choose the build option for each space from its space type.
- Write the swap sheet: position, old model, new model, hostname kept.
- Check mounts, cable lengths and power suit the new model (its ports are on the model page).
- List each networked device with its port and VLAN for the network team.
- Ask the service manager for design sign-off.
Who
- Marcus LeeLead engineer16 h estimatedDesign, signal routes, commissioning
Devices installed or changed
No devices were installed or changed by this work.
Evidence
- Closing note: Nothing new: the guide was right
- Recorded for the Design phase: Design drawings
- Recorded for the Design phase: Signal route per room
Deviations and added tasks
No deviations recorded.
Sign-off
- Design gate: signed off by Sofia Reyes, 19 Jun 2026