Keia Atlas · Work report
Survey both rooms and the ceiling
DoneGenerated 19 Oct 2026
- Task
- T-1801 Survey both rooms and the ceiling
- Project
- PRJ-18 Tokyo office hybrid meeting rooms
- Office
- Tokyo office
- Kind of work
- Plan phase, survey work
- Space
- Whole project
- Done by
- Kenji Sato, Technician
- Due
- 9 Oct 2026
- Estimate
- 6 h
- Closed with the phase
- Plan phase ended 25 Sept 2026
What was done
Survey both rooms and the ceiling. Nothing new: the guide was right.
Steps followed
- Open the space type drawing and walk the space with it.
- Check every outlet is where the space type expects it: power and data behind the display, under the table, at the door.
- Photograph the display wall, the table floor box and the ceiling.
- Note anything that differs from the space type; it goes in the design.
Who
- Kenji SatoTechnician6 h estimatedSurvey and installs
Devices installed or changed
No devices were installed or changed by this work.
Evidence
- Closing note: Nothing new: the guide was right
- Recorded for the Plan phase: Scope
Deviations and added tasks
No deviations recorded.
Sign-off
- Plan gate: signed off by Tomás Varga, 25 Sept 2026
- Task closed