Keia Atlas · Work report
Port map and cutover plan
DoneGenerated 19 Oct 2026
- Task
- T-1902 Port map and cutover plan
- Project
- PRJ-19 Melbourne office IDF switch refresh
- Office
- Melbourne office
- Kind of work
- Design phase, design work
- Space
- Whole project
- Done by
- Marco Bianchi, Network engineer
- Due
- 17 Sept 2026
- Estimate
- 12 h
- Closed with the phase
- Design phase ended 17 Sept 2026
What was done
Port map and cutover plan. Nothing new: not device related.
Steps followed
- Choose the build option for each space from its space type.
- Write the swap sheet: position, old model, new model, hostname kept.
- Check mounts, cable lengths and power suit the new model (its ports are on the model page).
- List each networked device with its port and VLAN for the network team.
- Ask the service manager for design sign-off.
Who
- Marco BianchiNetwork engineer12 h estimatedSwitch design and port map
Devices installed or changed
No devices were installed or changed by this work.
Evidence
- Closing note: Nothing new: not device related
- Recorded for the Design phase: Port map
Deviations and added tasks
No deviations recorded.
Sign-off
- Design gate: signed off by Declan Moore, 17 Sept 2026
- Task closed