Work reportDoneSimulated

Work report: Prove the fault: swap the cable, then try a bench receiver

Complete · 1 difference from the planchecked just now

Back to the task

Keia Atlas · Work report

Prove the fault: swap the cable, then try a bench receiver

DoneGenerated 19 Oct 2026

Task
T-2101 Prove the fault: swap the cable, then try a bench receiver
Project
PRJ-21 Heron HDBaseT receiver RMA
Office
Chicago office
Kind of work
Plan phase, survey work
Space
12.03 Heron
Done by
Grace Kim, Technician
Due
15 Oct 2026
Estimate
2 h
Closed with the phase
Plan phase ended 15 Oct 2026

What was done

Prove the fault: swap the cable, then try a bench receiver. Fix captured: A bench receiver is the fastest test on a passive HDBaseT run: it separated the receiver from the cable in one try.

Steps followed

  1. Open the space type drawing and walk the space with it.
  2. Check every outlet is where the space type expects it: power and data behind the display, under the table, at the door.
  3. Photograph the display wall, the table floor box and the ceiling.
  4. Note anything that differs from the space type; it goes in the design.

Who

  • Grace KimTechnician2 h estimatedProved the fault, runs the workaround and swaps the receiver

Devices installed or changed

No devices were installed or changed by this work.

Evidence

  • Closing note: A bench receiver is the fastest test on a passive HDBaseT run: it separated the receiver from the cable in one try.
  • Recorded for the Plan phase: Fault notes
  • Recorded for the Plan phase: RMA-55120

Deviations and added tasks

  • The guide did not cover this. Fix captured: A bench receiver is the fastest test on a passive HDBaseT run: it separated the receiver from the cable in one try.

Sign-off

  • Plan gate: signed off by David Okoro, 15 Oct 2026
  • Task closed
Done byGrace KimSignatureDate
Project managerDavid OkoroSignatureDate

View as

See Keia Atlas the way someone else does. A demo: nobody signs in.

Viewing asAnna ByrneAV and IT delivery engineer · EMEA

Suggested

Delivery

  • Delivery engineerDesigns and commissions spaces, from survey to handover
  • Project managerRuns projects day to day: dates, suppliers and who does what
  • On-site technicianInstalls and fixes kit in the offices
  • Programme managerPlans the year of projects across every region
  • Engineering managerLeads the delivery engineers
  • Project management leadLeads the project managers
  • On-site services managerLeads the on-site technicians
  • Delivery managerThe whole delivery team, every region

Support and service

  • Service desk analystTakes incidents as they arrive and routes them
  • Network engineerPorts, VLANs and patching
  • Service manager, AVOwns the AV standard and its service
  • Service manager, networkOwns the network standard and its service

The Lab

  • Innovation engineerTests new kit before it ships

Leadership

  • Head of AV and ITThe whole service, every region

Partners

  • Integration vendorSees their own installations only
  • Service vendorRepairs under the service contract

Overview

  • EveryoneEvery role's first screen at once, to see the whole picture

Settings

Appearance
LookStudio
Text size
Default

Report

Tell the team

About T-2101 Prove the fault: swap the cable, then try a bench receiver

Goes to Sofia Reyes, Service manager, AV. Reviewed within five working days.