| Sized for | Needs | Has | Verdict |
|---|---|---|---|
| Data outlets | 38 9 spaces, 5 video rooms | 48 | 10 to spare |
| Access ports | 46 38 + 20% headroom | 48 | 2 to spare |
| Access switches | 1 48 ports each | 1 | Exactly enough |
| PoE budget | 212 W 7 devices as the vendors state; 5 PoE devices with no figure | – | Not recorded |
| Rack space | 24U 16U of parts + 25% growth | 24U | Exactly enough |
| UPS | Not sized load and runtime not recorded | APC Smart-UPS SRT 3000VA, 2U | Not checked |
Vendor access
This part is for Aigna staff
Vendors see their own installation and the device reference they need to build it: device types, setup guides and models. Everything else stays with Aigna.
Go to your installationModule
Locations is switched off
Regions, offices, floors and the spaces in them. This demo has the Locations module switched off in Organisation settings.
OfficeSINAsia Pacific--:-- local · Simulated live
Singapore office
1 space not working nowchecked just now
Health of each space now. Simulated.
- Meeting rooms
- Focus, huddle and offices
- Print and storage
- Breakout
- Corridors
- Stairs
- Lifts
- Toilets
- Riser
- Comms room
- Stores and ducts
Key Health
- WorkingNothing wrong now; shaded darker while in use
- Not working nowA unit offline or alerting, or an open incident
- ClosedOutside the office's hours; no ring
- FaultA P1 to P3 incident someone is on, or nobody has yet
- To reviewA P4, or a job waiting on something outside
- Work bookedA task or a device swap, no incident
- No open jobsNothing open in the space
- FaultA switch port serving the space is down or draws no power
- To reviewA switch port serving it is off the VLAN plan, or a cable passed its test with little margin
- FineEvery port up; its access point in service
- Not recordedNo switch port recorded for the space
- PlannedIn a project that has not reached the space yet
- Being installedThe new kit is going in now
- Snag openInstalled, with a snag still open
- Handed overDone and handed over
- CoveredA vendor covers the kit; the contract runs past 90 days
- To reviewThe covering contract ends within 90 days
- Not coveredNo vendor recorded for the kit
- Guides and fixesSetup guides or captured fixes cover the kit
- Known errorA manufacturer's known error affects a unit here
- Guide past dueA setup guide is past due for review (dashed)
- Nothing recordedNo guide, known error or captured fix yet
Replay
NowSimulated. Frames are drawn still; Play steps them one by one. Space pauses, ← and → step, Now goes back to live.
Internet
- Carrier OnePrimary · Dedicated internet access over fibre, handed off as Ethernet · 1 Gb/s symmetric
IT store
- 12.14 IT store10 spare units · 1 counted line
- 2 below minimumLast counted 10 Oct 2026
Next two weeks
- Curlew's video bar shows no meetings, so we can't join with one touchUntil 19 Oct · Incident
- Replace 1 device due in 202619 Oct · Work plan
- Fix the calendar resource for Curlew and Robin21 Oct · Project task
- Add the five panels to monitoring and check each one reports23 Oct · Project task
Spaces by floor
9 spacesAll 10 spaces in Spaces →Twelfth floor 9 spaces
Comms rooms and racks
Cables at Singapore office →Internet circuits
Restricted: internet circuits Follow them in 3DOne circuit: 1 Gb/s primary
Carrier One
Primary1 Gb/s symmetric
- Circuit ID
- C1-SIN-0042288
- Service level
- 99.95% available, restored within 4 hours, 24/7
- Support
- Carrier One service desk, 24/7; account C1-ACC-40756
- Contract
- Renews 21 Mar 2028, 36-month term
- Kind
- Dedicated internet access over fibre, handed off as Ethernet
Carrier details are demo values Demo value. The carrier's phone number is kept in the paging tool, not here.
Open work and incidents
Projects 1
- Singapore office booking panelsPRJ-11 · Upgrade · Deploy
Incidents 1
- Curlew's video bar shows no meetings, so we can't join with one touchP3 INC0041180 · On hold · 12.03 Curlew
Vendors and visits
Vendors 1
- Brightwave IntegrationIntegration
Visits 1
- Comms room audit, Singapore office22 Dec 2026
Hours and change window
Open 07:00 to 19:00, Monday to Friday · next change window Thursday 22 Oct, 22:00 to 02:00
Office hours
07:00 to 19:00
Monday to Friday, Singapore time. Displays and signage turn on at opening and off an hour after closing.
Hours and window are demo values Demo value.
Facts
- Kind
- Regional office
- Where
- Singapore, Singapore
- Region
- Asia Pacific
- Time zone
- Asia/Singapore
- Floors
- Twelfth floor
- Spaces
- 9 spaces, 0 desks, 1 comms room
- Devices
- 46 units
- Mains
- 230 V, 50 Hz, plug G
- On-site technician
- Arjun Rao
- 3D model
- Modelled: every floor, comms room, cable run and circuit